Summary
The scrutiny surrounding the funding for the US Navy’s Virginia-class submarine program has intensified as lawmakers grapple with a projected $17 billion budget overrun and delays in construction. Recent legislative discussions have led to the postponement of a critical $1.95 billion funding decision, raising concerns about the program’s future and the Navy’s ability to meet its commitments.
In light of significant cost overruns and delayed timelines, House Defense Appropriations Chairman Ken Calvert highlighted the Navy’s lack of transparency regarding its financial needs. The House has opted to exclude the $1.95 billion funding request from a stopgap spending bill, which has prompted discussions about alternative funding frameworks, such as the Shipyard Accountability and Workforce Support (SAWS) initiative. This proposal aims to address inflation-related expenses and workforce pay issues by restructuring how contracts are managed with submarine builders. However, skepticism remains regarding the effectiveness of SAWS, with some lawmakers advocating for a more robust funding approach to ensure the Virginia-class program can proceed without further setbacks.
Key Issues
-
Budget Overruns: The Virginia-class submarine program is projected to exceed its budget by $17 billion through 2030, prompting concerns from lawmakers about the sustainability of the Navy’s shipbuilding efforts.
-
Construction Delays: Recent reports indicate that the Navy is struggling to meet its production targets, constructing only 1.3 submarines per year instead of the required two, with significant delays affecting multiple shipbuilding projects.
-
Legislative Response: The omission of the $1.95 billion funding from the continuing resolution reflects the complexities of the current budget negotiations, with lawmakers seeking clarity from the Navy on its funding needs and potential alternatives.
Future Considerations
-
SAWS Initiative: The proposed SAWS initiative aims to alleviate financial pressures by allowing the industry to access funds earlier in the contract cycle. However, its viability and potential impact on the Virginia-class program remain under scrutiny.
-
Commitments to AUKUS: The delays and funding issues could jeopardize the US’s ability to fulfill commitments under the AUKUS agreement, which includes providing Virginia-class submarines to Australia.
As discussions continue, the future of the Virginia-class submarine program hangs in the balance, with lawmakers emphasizing the need for a dependable production schedule and effective funding solutions to address the challenges at hand.
Lawmakers postpone decision on Virginia-class submarine money
Sep. 24 / Roll Call “ With the exclusion of nearly $2 billion for a major naval effort from the bipartisan stopgap spending bill, lawmakers have effectively punted a decision on...
US Navy's new submarines are 'in crisis' as costs balloon by $17 billion, lawmaker says
Sep. 20 / Business Insider “ The US Navy's Virginia-class submarine program is projected to run $17 billion over budget through 2030. The Navy is expected to build two Virginia subs a...